The list of contracts of the Tandem project, LLC in 2019


Client The appellation of the contract Period of execution of works
1 Argent alliance, LLC Reconstruction of the sea pier in Foros March 2019 -
November 2020
2 Administration of the Yuryevets municipal district of the Ivanovo region Reconstruction of the protective dam of the engineering protection of the town of Yuryevets of the Ivanovo region (Adjustment taking into account the work performed on the reconstruction and overhaul) June 2019 -
December 2022
3 Administration of the urban district of Shchelkovo of the Moscow region Execution of work on the overhaul of a collector 2D = 1200mm (two lines), passing in a reinforced concrete siphon along the bottom of the Klyazma River and in the adjacent coastal zone, Shchelkovsky region July 2019 -
April 2021
4 State unitary enterprise of the republic of Crimea "Water of Crimea" Construction and installation works at the site: "Overhaul of the deep-water outlet of the WWTP in Alushta" July 2019 -
December 2020
5 State unitary enterprise of the republic of Crimea "Water of Crimea" Construction and installation works at the site: "Overhaul of the deep-water discharge of WWTP in Solnechnogorskoye settlement" July 2019 -
December 2020
6 State unitary enterprise of the republic of Crimea "Water of Crimea" Construction and installation works at the site: "Overhaul of the deep-water discharge of WWTP in Partenit settlement" July 2019 -
December 2020
7 State unitary enterprise of the republic of Crimea "Water of Crimea" Construction and installation works at the site: "Overhaul of the deep-water discharge of WWTP in Rybachye" July 2019 -
December 2020
8 8 state unitary enterprise of the republic of Crimea "Water of Crimea" Construction and installation works at the site "Overhaul of the deep-water discharge of WWTP in Primorsky" September 2019 -
December 2020
9 State unitary enterprise of the republic of Crimea "Vodokanal uzhnogo berega Kryma, sue rk" Construction and installation works at the site "Overhaul of deep-water outlets of WWTP, Republic of Crimea:" Overhaul of deep-water outlet of WWTP in Gurzuf settlement" July 2019 -
December 2020
10 State unitary enterprise of the republic of Crimea "Vodokanal uzhnogo berega Kryma, sue rk" Construction and installation works at the site "Overhaul of deep-water outlets of WWTP, Republic of Crimea:" Overhaul of deep-water outlet of Yalta WWTP, Otradnoye" July 2019 -
December 2021
11 State unitary enterprise of the republic of Crimea "Vodokanal uzhnogo berega Kryma, sue rk" Construction and installation works at the site "Overhaul of deep-water outlets of WWTP, Republic of Crimea:" Overhaul of deep-water outlet of WWTP in Simeiz" July 2019 -
December 2021
12 State unitary enterprise of the republic of Crimea "Vodokanal uzhnogo berega Kryma, sue rk" Construction and installation works at the site "Overhaul of deep-water outlets of WWTP, Republic of Crimea:" Overhaul of deep-water outlet of WWTF in Foros" July 2019 -
December 2020
13 EuroChem (Murmansk berth №19) Complex repairs of berth № 19 July 2019 -
October 2019
14 Ural steel, LLP Cleaning the bottom of the bucket intake of the pumping station of the 1st lift November 2019 -
October 2020